UEDCL begins Shs931m Masaka power line upgrade to improve supply

The works include replacing the existing 75mm² overhead conductors with larger 150mm² conductors, upgrading underground cables, replacing more than 70 deteriorated poles and upgrading current transformers that support the line’s protection systems.

UEDCL officials at the commencement of the Shs931 million upgrade of the Masaka Central–Masaka West 33kV interconnector, which is expected to improve electricity supply reliability across Greater Masaka. (Photo via @GovUganda)

In Summary: UEDCL is refurbishing the 7.6-kilometre Masaka Central–Masaka West interconnector, replacing conductors, cables and more than 70 deteriorated poles. The company says the line is linked to about nine in every 10 interruptions on its medium-voltage network in Masaka. The works are expected to be completed by the end of January 2027.

Masaka, Uganda — The Uganda Electricity Distribution Company Limited (UEDCL) has commenced a Shs931 million upgrade of the Masaka Central–Masaka West 33kV interconnector, a critical distribution line expected to improve electricity supply reliability for more than 130,000 customers across Greater Masaka.

The four-month project involves refurbishing the existing 7.605-kilometre overhead power line connecting the Masaka West and Masaka Central substations.

The works include replacing the existing 75mm² overhead conductors with larger 150mm² conductors, upgrading underground cables, replacing more than 70 deteriorated poles and upgrading current transformers that support the line’s protection systems.

Article continues below

The project will also involve installing larger 300mm² underground cables along a 190-metre section, replacing the existing 150mm² cables, and using concrete poles in swampy areas to improve infrastructure durability.

The upgrade is intended to address persistent electricity supply challenges in Greater Masaka, where growing demand from households, businesses and industrial consumers has placed increasing pressure on the existing distribution network.

Speaking at the commencement of the works, UEDCL Territory Manager for Greater Masaka, Benjamin Busingye, said the old and overloaded interconnector had been responsible for a significant proportion of electricity interruptions in the area.

“This interconnector contributes approximately 90 per cent of the interruptions we experience on our medium-voltage network in Masaka. Out of every ten interruptions, about nine are associated with this line. Refurbishing it is therefore a major intervention towards improving the reliability of electricity supply for our customers,” Busingye said.

He noted that electricity demand in Greater Masaka had more than doubled over the past seven years, increasing from approximately 15MVA to more than 30MVA, making the upgrade necessary to accommodate the area’s growing energy requirements.

The Senior Territory Engineer for Greater Masaka, Eng. Bruce Kizito, explained that the existing 75mm² conductor was designed to carry a maximum capacity of approximately 20MVA, which had become inadequate for the area’s increasing demand.

“We are upgrading the conductor from 75mm², which can carry up to 20MVA, to 150mm², which will increase the line’s capacity to approximately 30MVA. This will enable us to accommodate the growing electricity demand in Greater Masaka,” Eng. Kizito explained.

He added that the associated underground cables were also being upgraded to ensure that the entire interconnector could handle the increased capacity.

The upgrade is expected to benefit customers in Masaka City and the districts of Masaka, Kalungu, Bukomansimbi, Kalangala, Kyotera and Sembabule, as well as parts of Mpigi District, particularly Kayabwe and Buwama.

Beyond the refurbishment of the existing line, UEDCL is also pursuing the construction of a second interconnector between the Masaka West and Masaka Central substations.

The additional line will provide an alternative supply route, allowing electricity distribution to be switched between the two lines whenever one experiences a fault or requires maintenance.

The refurbishment works are expected to be completed by the end of January 2027, with the additional interconnector forming part of UEDCL’s broader efforts to strengthen electricity supply infrastructure in the region.

UEDCL has called on customers and members of the public to protect electricity infrastructure and report vandalism or suspicious activity around power installations, noting that damage and theft of network equipment undermine efforts to improve supply reliability.

If you would like your article/opinion to be published on Uganda’s most authoritative news platform, send your submission on: [email protected]. You can also follow DailyExpress on WhatsApp and on Twitter (X) for realtime updates.



Daily Express is Uganda's number one source for breaking news, National news, policy analytical stories, e-buzz, sports, and general news.

We resent fake stories in all our published stories, and are driven by our tagline of being Accurate, Fast & Reliable.

Copyright © 2026 Daily Express Uganda. A Subsidiary of Rabiu Express Media Group Ltd.

To Top
Translate »